iMonitor Settings
OEE Availability = Operating Time / Planned Production Time
Planned Production Line settings
If no schedule is set the default scheduled time will be 24/7.
Once a schedule has been set up a schedule will always be required.
Operating Time
The operating time calculation can be configured by selecting a machine state.
- Will include in the OEE Operating Time calculation.
- Will excluded in the OEE Operating Time calculation.
Performance = (Total Pieces * Ideal Cycle Time) / Available Time
Ideal Cycle time settings
The ideal cycle time calculation can be configured by inputting the expected units per hour